Isthmus Bay Road Reconstruction - Phase 3

The Municipality is reconstructing Isthmus Bay Road from the Swan Lake Bridge to the intersection of Forty Hills Road/Whippoorwill Road. The project, set to commence on September 19, 2022, will improve road infrastructure and will add a new asphalt road surface. Further information can be obtained from the Notice to Residents

Anticipated timeline

Construction is expected to finish for the 2022 season by November 1. 

Contact us

Troy Cameron, Public Works Manager
Municipality of Northern Bruce Peninsula
pwmanager@northernbruce.ca
(519) 793-3522 ext. 232

Jason Mervyn, Site Inspector
GSS Engineering Consultants Ltd.
jasonmervyn@gssengineering.ca
(519) 372-4828

Ross Slaughter, Project Engineer
GSS Engineering Consultants Ltd. 
rossslaughter@gssengineering.ca
(519) 372-4828